Jaw crusher installation technical requirements

11-19-2012

The important part of the long-term as the stone first broken jaw crusher, its assembly technology also has been a top priority. Moving  jaw crusher assembly technology focus in the assembly, and the workload of the assembly work is also focused on moving the jaw, movable jaw assembly is mainly concentrated in the 4 groups Rolling on. If these four groups bearing assembly was to meet the technical requirements, and reeved moving jaw and very smooth, not to simmer fresh, the assembly dimensions are in line with the requirements of the drawings, the whole machine the run estimated will not appear big problem.

The following details about the technical requirements of the installation of the jaw crusher:

Assembly base should meet the following requirements:

Prescribed position the joints should be designed to locate and install all the locating pin;

Joint surface contact should close, when the bolts are not tightened, the 0.10mm feeler checks shall not be inserted into the local gap segment length should not be more than 100mm, the cumulative length should not exceed 10% of the total length of the joint surface edge;

Frame connecting bolt preload shall comply with the provisions of the equipment technical documentation, tighten should be the order of symmetry, the force should be uniform;

The base longitudinally mounted level should not be greater than 0.50/1000 horizontal installation level should not be greater than 0.20/1000, spindle and bearing the carved surface measurements;

Parts of the jaw crusher stand above, should be in the base alignment, leveling and tighten the anchor bolts, square was assembled.

T-shaped head anchor, its specifications should be consistent with the requirements of the design, installation should be perform mechanical equipment installation engineering construction and acceptance of universal norms, "the provisions of the existing national standards;

Pad toggle plate and toggle plate should contact evenly, per meter length of the gap should not be greater than 1.5mm; jaw bearing surface shall be uniform contact its gap should jaw size into account, should not be greater than 3 mm per meter.

Rolling assembly shall comply with the provisions of the technical documentation of the device.

Thank you for your interest in YIFAN. Please use any of the methods below to get in touch with us.
Add: The Middle of Zhengyuan Road, Xingyang Eastern Development Zone.
zip:450100
E-mail:yifanseo@yfmac.com
Tel: +86-371-64966831 Fax: +86-371-64628872
The article by jaw crusher,jaw crushers YIFAN Machinery Editor: http://www.jawcrushers.org/, please indicate the source , little effort , thank you .

Case
You are here:Jaw Crusher>> News>>Jaw crusher installation technical requirements